Work accomplished this past week of April 7, was as follows:

  • Paving of the southern half of the Rochambeau Bridge
  • Began paving the median crossover on the Southbury side of the bridge and placed/graded/compacted processed aggregate base for the median crossover on the Newtown side.

The Contractor will be not be working Friday, April 15, or over this weekend. 

During the week of April 18, the paving of median crossover on the Southbury side will be completed, followed by the paving of the crossover on the Newtown side. 

We anticipate shifting Eastbound traffic into the crossovers across the southern half of the Westbound bridge during night shift the week of April 25.  Once traffic is shifted, demolition of the existing Eastbound bridge will commence.

Menu