This past week of April 10, we accomplished the following work:

  • Completed applying the waterproof membrane on the bridge deck
  • Removed remaining barges in the channel & crane
  • Continued forming and pouring the EB Concrete barrier wall
  • Continued existing substructure concrete spot repair
  • Continued to install rip-rap for slope protection
  • Continued to rub and grind parapet concrete
  • Began full depth reconstruction of the roadway on EB Southbury side
  • Continued to monitor and control environmental BMPs

The Contractor will have crews working Saturday April 8.

During the week of April 17, we will continue to:

  • Form and pour the EB Concrete barrier wall
  • Perform full-depth reconstruction of the roadway on EB Southbury side
  • Spot repair existing substructure concrete
  • Install rip-rap for slope protection
  • Rub and grind parapet concrete
  • Monitor and control environmental BMPs