This past week of April 4, the following work was accomplished:
- Placed membrane waterproofing on the south side of the new Westbound deck.
- Placed processed aggregate base for the Eastbound crossovers in the median on both sides of the bridge.
Beginning Monday, April 11, paving of the deck and crossovers will take place.
We anticipate shifting Eastbound traffic into the crossovers across the southern half of the Westbound bridge the week of April 25.
Once traffic is shifted, demolition of the existing Eastbound bridge will commence.
No work will take place on Good Friday, April 15 or on Easter weekend.