This past week of April 3, we accomplished the following work:

  • Completed bridge deck surface prep for application of the waterproof membrane
  • Began application of the waterproof membrane for the Eastbound bridge deck
  • Continued preparation to form and pour, and restore the concrete sidewalk pedestrian path
  • Completed removal of the temporary trestle
  • Continued to install navigation lighting (red) on the I-84 EB bridge
  • Continued existing substructure concrete spot repair
  • Continued to install rip-rap for slope protection
  • Continued to rub and grind parapet concrete
  • Continued to monitor and control environmental BMPs

The Contractor will have crews working tomorrow Saturday, April 8.

During the week of April 10, we will continue to:

  • Apply the waterproof membrane on the bridge deck
  • Install navigation lighting (red) on the I-84 EB bridge
  • Spot-repair existing substructure concrete
  • Install rip-rap for slope protection
  • Rub and grind parapet concrete
  • Monitor and control environmental BMPs