This past week of April 3, we accomplished the following work:
- Completed bridge deck surface prep for application of the waterproof membrane
- Began application of the waterproof membrane for the Eastbound bridge deck
- Continued preparation to form and pour, and restore the concrete sidewalk pedestrian path
- Completed removal of the temporary trestle
- Continued to install navigation lighting (red) on the I-84 EB bridge
- Continued existing substructure concrete spot repair
- Continued to install rip-rap for slope protection
- Continued to rub and grind parapet concrete
- Continued to monitor and control environmental BMPs
The Contractor will have crews working tomorrow Saturday, April 8.
During the week of April 10, we will continue to:
- Apply the waterproof membrane on the bridge deck
- Install navigation lighting (red) on the I-84 EB bridge
- Spot-repair existing substructure concrete
- Install rip-rap for slope protection
- Rub and grind parapet concrete
- Monitor and control environmental BMPs