This past week of October 3, 2022, we accomplished the following work:

  • Completed structural steel erection
  • Continued installation of temporary overhang brackets and edge forms
  • Rub and grind completed concrete surfaces at Piers 2 & 3 and Abutments 1 & 2
  • Continued earthwork behind Abutment 1 and Abutment 2
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working Saturday, October 8.

During the week of October 10, 2022, we will:

  • Remove temporary steel erection supports
  • Continue to install temporary overhang brackets and edge formwork
  • Continue to bolt and torque down steel connections
  • Begin installation of stay-in-place deck forms and shear stud connectors
  • Continue earthwork at Abutment 1 and Abutment 2

Channel Update:

  • Steel erection work over the channel is complete.
  • The channel will be open.