This past week of February 27, we accomplished the following work:

  • Completed partial installation of the navigation lighting (green) on the I-84 EB Bridge
  • Completed abutment wingwall extension walls
  • Completed installation of the Abutment 1 finger joint assembly
  • Completed the removal of overhang brackets
  • Completed snow removal operations following Tuesday’s snow event
  • Continued the removal of the temporary work trestle on the Southbury side
  • Continued to monitor and control environmental BMPs

The Contractor will not have crews working this weekend.

During the week of March 6, we will continue to:

  • Install navigation lighting (red) on the I-84 EB Bridge
  • Install rip-rap for slope protection
  • Remove temporary trestle operations
  • Monitor and control environmental BMPs