This past week of February 27, we accomplished the following work:
- Completed partial installation of the navigation lighting (green) on the I-84 EB Bridge
- Completed abutment wingwall extension walls
- Completed installation of the Abutment 1 finger joint assembly
- Completed the removal of overhang brackets
- Completed snow removal operations following Tuesday’s snow event
- Continued the removal of the temporary work trestle on the Southbury side
- Continued to monitor and control environmental BMPs
The Contractor will not have crews working this weekend.
During the week of March 6, we will continue to:
- Install navigation lighting (red) on the I-84 EB Bridge
- Install rip-rap for slope protection
- Remove temporary trestle operations
- Monitor and control environmental BMPs