This past week of March 13, we accomplished the following work:

  • Completed installation of Abutment 2 approach slab formwork and reinforcing bar installation
  • Completed concrete pour for the Abutment 2 approach slab
  • Continued the removal of the temporary work trestle on the Southbury side
  • Continued rubbing and grinding the bridge parapets
  • Continued the installation of rip-rap for slope protection
  • Continued existing substructure concrete spot repair
  • Continued to monitor and control environmental BMPs

The Contractor will have crews working tomorrow, Saturday March 18.

During the week of March 20, we will:

  • Install the Abutment 2 finger joint assembly
  • Continue to install navigation lighting (red) on I-84 EB Bridge
  • Continue existing substructure concrete spot repair
  • Continue to install rip-rap for slope protection
  • Continue to rub and grind parapet concrete
  • Continue removal of temporary trestle operations
  • Continue to monitor and control environmental BMPs