This past week of March 13, we accomplished the following work:
- Completed installation of Abutment 2 approach slab formwork and reinforcing bar installation
- Completed concrete pour for the Abutment 2 approach slab
- Continued the removal of the temporary work trestle on the Southbury side
- Continued rubbing and grinding the bridge parapets
- Continued the installation of rip-rap for slope protection
- Continued existing substructure concrete spot repair
- Continued to monitor and control environmental BMPs
The Contractor will have crews working tomorrow, Saturday March 18.
During the week of March 20, we will:
- Install the Abutment 2 finger joint assembly
- Continue to install navigation lighting (red) on I-84 EB Bridge
- Continue existing substructure concrete spot repair
- Continue to install rip-rap for slope protection
- Continue to rub and grind parapet concrete
- Continue removal of temporary trestle operations
- Continue to monitor and control environmental BMPs