This past week of March 6, we accomplished the following work:
- Completed concrete pours for abutment wingwall extension walls
- Completed subgrade for the Abutment 2 approach slab
- Began installation of Abutment 2 approach slab formwork and reinforcing bar installation
- Continued the removal of the temporary work trestle on the Southbury side
- Continued to monitor and control environmental BMPs
The Contractor will not have crews working this weekend.
During the week of March 13, we will continue:
- Installation of Abutment 2 approach slab formwork and reinforcing bar
- Installation of navigation lighting (red) on I-84 EB bridge
- Spot repair of existing substructure concrete
- Installation of rip-rap for slope protection
- Removal of temporary trestle operations
- Monitoring and control of environmental BMPs