Update: March 13, 2023

  1. Home
  2. News
  3. Update: March 13, 2023

This past week of March 6, we accomplished the following work:

  • Completed concrete pours for abutment wingwall extension walls
  • Completed subgrade for the Abutment 2 approach slab
  • Began installation of Abutment 2 approach slab formwork and reinforcing bar installation
  • Continued the removal of the temporary work trestle on the Southbury side
  • Continued to monitor and control environmental BMPs

The Contractor will not have crews working this weekend.

During the week of March 13, we will continue:

  • Installation of Abutment 2 approach slab formwork and reinforcing bar
  • Installation of navigation lighting (red) on I-84 EB bridge
  • Spot repair of existing substructure concrete
  • Installation of rip-rap for slope protection
  • Removal of temporary trestle operations
  • Monitoring and control of environmental BMPs

Menu