This past week of January 2, we continued to:

  • Install parapet and safety curb reinforcing steel
  • Form the abutment wingwall extension walls
  • Form and pour the bridge parapet and safety curb
  • Rub and grind poured parapet sections
  • Load out flexi-float barge sections
  • Monitor and control environmental BMPs

The Contractor will not be working this weekend.

During the week of January 9, we will continue to:

  • Install parapet and safety curb reinforcing steel
  • Form and pour the bridge parapet and safety curb
  • Rub and grind completed parapet sections
  • Remove overhang brackets
  • Monitor and control environmental BMPs

Channel Update: The boating channel is open.