This past week of December 26, we accomplished the following work:
- Continued to install parapet and safety curb reinforcing steel
- Continued to form the abutment wingwall extension walls
- Continued to form and pour the bridge parapet and safety curb
- Completed demobilization of one of the Link-Belt cranes
- Continued to monitor and control environmental BMPs
The Contractor will not be working this weekend, Dec. 31 & Jan. 1
During the week of January 2, 2023, we will continue to:
- Install parapet and safety curb reinforcing steel
- Form and pour the bridge parapet and safety curb
Channel Update: The boating channel is open.
Have a Happy New Year’s celebration!