This past week of January 9, we accomplished the following work:

  • Continued to install parapet and safety curb reinforcing steel
  • Continued to form the abutment wingwall extension walls
  • Continued to form and pour the bridge parapet and safety curb
  • Continued to rub and grind poured parapet sections
  • Continued to remove overhang brackets
  • Began installation of permanent bridge drainage downspouts
  • Continued to monitor and control environmental BMPs

The Contractor will not be working this weekend.

During the week of January 16, we will continue to:

  • Install parapet and safety curb reinforcing steel
  • Form and pour the bridge parapet and safety curb
  • Rub and grind completed parapet sections
  • Remove overhang brackets
  • Install permanent bridge drainage downspouts
  • Monitor and control environmental BMPs

Channel Update: The boating channel is open.