No work is anticipated Saturday through Monday, 5/29 – 5/31, over the Memorial Day weekend.
This past week we poured concrete at the Pier 1 Cap (see photos below).
Next week, from Tuesday, June 1, we will continue modifications of abutment footings and reconstructing tops of Pier 2. Work will continue at the cofferdam of Pier 3 using large sandbags to surround the pier and pumping out the water inside so material can be excavated and modifications there can be performed in the dry.
Boaters, please be cautioned that the Project currently maintains a ‘Slow – No Wake’ speed restriction through the channel at all times, even on weekends when there is no work. Read more.