No work is anticipated Saturday, May 22.
During the week of May 24, we will continue modifications of abutment footings and reconstructing tops of and piers. The pier cap at Pier 1 (photos below) is scheduled to be poured mid-week. Work will continue at the cofferdam of Pier 3 using large sandbags to surround the pier and pumping out the water inside so modifications there can be performed in the dry.