This past week of November 28, we accomplished the following work:

  • Completed and began curing of deck pour #4 and #5
  • Continued to form the abutment wingwall extension walls
  • Continued installation of Westbound bridge scuppers
  • Continued to install galvanized deck reinforcing steel
  • Contractor loaded out flexi-float material barges
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will not be working over the weekend.

During the week of December 5, we will:

  • Complete installation of deck reinforcing bars
  • Complete installation of bridge scuppers
  • Continue to form, pour, and cure final concrete deck sections – Deck Pours 6 & 7
    Continue to form abutment wingwall extensions walls
  • Begin installation of galvanized parapet reinforcing steel
  • Begin to form and pour the bridge parapet and safety curb

Channel Update: The boating channel is open.