This past week of December 12, we accomplished the following work:

  • Began to pour concrete parapets
  • Continued to install parapet and safety curb reinforcing steel
  • Continued to form the abutment wingwall extension walls
  • Repaired the temporary drainage downspout at the northern girder fascia of the bridge
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will not be working this weekend.

During the week of December 19, we will continue to:

  • Cure final concrete deck sections – deck pours 6 & 7
  • Form abutment wingwall extensions walls
  • Install parapet and safety curb reinforcing steel
  • Form and pour the bridge parapet and safety curb

Channel Update: The boating channel is open.

Menu