- John Lee, PE, District Engineer
- Judith Nemecek, PE, Assistant District Engineer
- Shawn Beaulieu, PE, Supervising Engineer
- Jesse Menzies, Project Engineer
Key Project Personnel
CTDOT
Middlesex Corporation
- John Cavatorta, VP of Construction Operations
- Andrew Walter, PE, Project Manager
- Noel Kelly, Project Superintendent
FHWA
Ted Alderi, Area Engineer
Lochner
Christopher Hylas, PE, Resident Engineer
WSP (LOUIS BERGER)
Shaun Seuhr, PE, Project Manager
James Hund, PE, Designer
AECOM
Ginger Manning, Public Involvement Specialist
FAQs
The existing bridges have extra-wide shoulders, so there is sufficient room to place bidirectional traffic, with two lanes in each direction, on one of the bridges while the other bridge is reconstructed. The first major traffic shift has placed both directions of I-84 traffic on I-84 eastbound utilizing crossovers built in the median of I-84. The I-84 westbound bridge is currently being partially demolished and reconstructed while this shift is in place.
Once the new I-84 westbound bridge is completed, traffic will be shifted onto the new bridge while the I-84 eastbound bridge is reconstructed, with temporary crossovers built in a similar manner, in the median of I-84.
Work in the river will take place using work trestles and barges. A minimum 75’ channel width for boaters will be maintained at all times, except for major demolition and steel erection work, which requires the advanced approval of Connecticut Department of Energy and Environmental Protection (DEEP), US Coast Guard and the Lake Zoar Authority.
The project was awarded to Middlesex Corporation at a cost of $52,873,000, on May 13, 2020.
The project is scheduled to be completed by December 23, 2023.