No work is scheduled for Saturday, May 1.

During the week of May 3, we will be completing the construction of the trestle finger at Pier 3 and continue reconstructing tops of abutments and piers, which includes:

  • Concrete removal;
  • Drilling and grouting new reinforcing steel;
  • Placing formwork and pouring concrete.

We also will continue prefabrication of rebar cages for the pier caps.