Removal of structural steel from the existing WB bridge will continue during the week of March 22, 2021, and is anticipated to be completed by the end of the week.
- Steel will be cut into smaller sections and transported off site.
- Reconstruction of the tops of abutments and piers has begun and will continue during the week of March 22.
- The contractor will not be working on Saturday, March 20.
The navigation channel beneath the bridge has been reopened.