Construction Update – Week of April 26, 2021

  1. Home
  2. Construction Alerts
  3. Construction Update – Week of April 26, 2021

There will be no work Saturday, April 24.

The week of April 26 we will be driving pile and constructing the trestle finger at Pier 3, and will continue reconstructing tops of the abutments and Piers 1 & 2, which includes:

  • Concrete removal;
  • Drilling and grouting new reinforcing steel;
  • Placing formwork and pouring concrete.

We are also prefabricating rebar cages for the pier caps.