Construction Update – Week of April 19, 2021

  1. Home
  2. Construction Alerts
  3. Construction Update – Week of April 19, 2021

There will be no work Saturday, April 17.

The week of April 19, workers will be driving pile for trestle finger at Pier 3 and will continue reconstructing tops of abutments and Piers 1 & 2, which includes:

  • Concrete removal
  • Drilling and grouting new reinforcing steel
  • Placing formwork and pouring concrete