No work is anticipated over the weekend of April 10-11.
Underdecking work for eastbound bridge is completed for now.
During the week of April 12, workers will continue reconstructing the tops of the piers and abutments.
Construction of the trestle finger, underneath the old westbound bridge to access Pier 3, will begin; this is required because the water at Pier 3 is not deep enough for using a barge.