This past week of September 11, we accomplished the following work: Continued final planting in the Southbury median Began wildflower establishment in the Newtown medians Continued grading & topsoiling in…
This past week of September 4, we accomplished the following work: Began final planting in the Southbury median Continued to haul material to the temporary re-use stockpile area (TRSA) Continued…
This past week of August 28, we accomplished the following work: Completed grading the water quality swale in Southbury Removed the topsoil screener off site Continued to haul material to…
During the past week of Aug 21, we continued the following work: Installation of the water quality swale in Southbury Final plantings Screening of topsoil for use on site Movement…
This past week of August 7, we accomplished the following work: Completed rumble strips project-wide Continued to install the water quality swale in Southbury Continued final plantings Continued to screen…
This past week of July 31, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area (TRSA) Completed installation of metal beam…
This past week of July 23, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area TRSA Completed the water quality swale…
This past week of July 16, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area (TRSA) Continued to install the water…
This past week of July 10, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area (TRSA) Continued to install the water…
This past week of July 3, we accomplished the following work: Continued to restore access roads using material from the TRSA Continued to install the water quality swale Southbury &…
This past week of June 26, we accomplished the following work: Continued to restore access roads using material from the TRSA Continued to install the water quality swale in Southbury…
Construction and Maintenance Activities Restricted for Upcoming Independence Day There will be no maintenance or construction activities within the Rochambeau Project limits that would require lane closures over the Independence…
This past week of June 19, we accomplished the following work: Continued to shift precast barrier on Westbound I-84 Continued to restore access roads using material from the temporary re-use…
This past week of June 12, we accomplished the following work: Finished installation of protective fence across the Eastbound bridge Continued to install rip-rap for slope protection under the Eastbound…
This past week of June 5, we accomplished the following work: Milled, paved, and striped I-84 EB tie-ins Opened EB I-84 in its final alignment over the eastbound bridge Continued…
This past week of May 29, we accomplished the following work: Continued to restore access roads using material from the temporary re-use stockpile area (TRSA) Continued to install of protective…
There will be a traffic shift at the Rochambeau Bridge, to place I-84 Eastbound (EB) traffic in its permanent alignment on final pavement across the new I-84 EB portion of…
This past week of May 15, we accomplished the following work: Completed metal beam rail on the eastbound bridge Continued to restore access roads using material from the TRSA Continued…
This past week of May 8, we accomplished the following work: Completed sidewalks from Fishrock Rd. to Underhill Rd. Continued to grade for metal beam rail Completed initial final paving…
Last week (week of May 1), we accomplished the following work: Completed EB milling Began installing a rip-rap swale from Alpine Dr. to the Rochambeau Bridge Continued to form and…
This past week of April 24, we accomplished the following work: Continued to form and pour sidewalk on both ends of the I-84 EB bridge Continued to grade for the…
This past week of April 17, we accomplished the following work: Completed forming and pouring the EB concrete barrier wall Continued existing substructure concrete spot repair Continued to install rip-rap…
This past week of April 10, we accomplished the following work: Completed applying the waterproof membrane on the bridge deck Removed remaining barges in the channel & crane Continued forming…
This past week of April 3, we accomplished the following work: Completed bridge deck surface prep for application of the waterproof membrane Began application of the waterproof membrane for the…
This past week of March 27, we accomplished the following work: Began bridge deck surface prep for application of the waterproof membrane Began preparation to form and pour, and restore…
This past week of March 20, we accomplished the following work: Completed installation of Abutment 2 finger joint assembly Resumed drainage work for final highway stormwater collection Continued the removal…
This past week of March 13, we accomplished the following work: Completed installation of Abutment 2 approach slab formwork and reinforcing bar installation Completed concrete pour for the Abutment 2…
This past week of March 6, we accomplished the following work: Completed concrete pours for abutment wingwall extension walls Completed subgrade for the Abutment 2 approach slab Began installation of…
This past week of February 27, we accomplished the following work: Completed partial installation of the navigation lighting (green) on the I-84 EB Bridge Completed abutment wingwall extension walls Completed…
Over the three-week period from February 13 to March 3, the contractor will: Begin work trestle removal operations Begin installation of finger joints and sliding protective plates Complete removal of…
This past week of February 6, we accomplished the following work: Began backfill and fine grading for the abutment approach slabs Completed dampproofing of the below grade abutment concrete surfaces…
This past week of January 30, we accomplished the following work: Completed the installation of parapet and safety curb reinforcing steel Completed concrete pours for the safety curb Continued to…
This past week of January 23, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…
This past week of January 16, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…
This past week of January 9, we accomplished the following work: Continued to install parapet and safety curb reinforcing steel Continued to form the abutment wingwall extension walls Continued to…
This past week of January 2, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…
We kicked off 2022 by implementing the Westbound Crossover alignment on Jan 4, 2022. The Contractor then performed some further clearing and grubbing which allowed them to construct two temporary…
This past week of December 26, we accomplished the following work: Continued to install parapet and safety curb reinforcing steel Continued to form the abutment wingwall extension walls Continued to…
This past week of December 19, we accomplished the following work: Continued to install parapet and safety curb reinforcing steel Continued to form the abutment wingwall extension walls Continued to…
This past week of December 12, we accomplished the following work: Began to pour concrete parapets Continued to install parapet and safety curb reinforcing steel Continued to form the abutment…
This past week of December 5, we accomplished the following work: Completed installation of galvanized deck reinforcing steel Completed installation of bridge scuppers Completed and began curing of final deck…
This past week of November 28, we accomplished the following work: Completed and began curing of deck pour #4 and #5 Continued to form the abutment wingwall extension walls Continued…
This past week of November 21, we accomplished the following work: Continued to place deformed steel bars for the eastbound bridge deck Poured concrete at the third of seven sections…
This past week of November 14, we accomplished the following work: Completed and began curing of deck pour #2 Continued to form the abutment wingwall extension walls Continued installation of…
This past week of November 7, we accomplished the following work: Began to form the abutment wingwall extension walls Began installation of parapet mounted multi-duct conduit Began installation of Westbound…
This past week of October 31, 2022, we accomplished the following work: Began to form the abutment wingwall extension walls Continued installation of stay-in-place deck forms, foam filler, and shear stud…
This past week of October 24, we accomplished the following work: Continued installation of stay-in-place deck forms and shear stud connectors Began installation of deck reinforcement Continued to rub and…
This past week of October 17, we accomplished the following work: Continued installation of stay-in-place deck forms and shear stud connectors Continued installation of temporary overhang brackets and edge forms…
This past week of October 10, 2022, we accomplished the following work: Completed bolting and torque down of steel connections Continued to remove temporary steel erection supports Continued installation of…
This past week of October 3, 2022, we accomplished the following work: Completed structural steel erection Continued installation of temporary overhang brackets and edge forms Rub and grind completed concrete…