This past week of March 20, we accomplished the following work: Completed installation of Abutment 2 finger joint assembly Resumed drainage work for final highway stormwater collection Continued the removal…
This past week of March 13, we accomplished the following work: Completed installation of Abutment 2 approach slab formwork and reinforcing bar installation Completed concrete pour for the Abutment 2…
This past week of February 27, we accomplished the following work: Completed partial installation of the navigation lighting (green) on the I-84 EB Bridge Completed abutment wingwall extension walls Completed…
Over the three-week period from February 13 to March 3, the contractor will: Begin work trestle removal operations Begin installation of finger joints and sliding protective plates Complete removal of…
This past week of February 6, we accomplished the following work: Began backfill and fine grading for the abutment approach slabs Completed dampproofing of the below grade abutment concrete surfaces…
This past week of January 30, we accomplished the following work: Completed the installation of parapet and safety curb reinforcing steel Completed concrete pours for the safety curb Continued to…
This past week of January 23, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…
This past week of January 16, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…
This past week of January 9, we accomplished the following work: Continued to install parapet and safety curb reinforcing steel Continued to form the abutment wingwall extension walls Continued to…
This past week of January 2, we continued to: Install parapet and safety curb reinforcing steel Form the abutment wingwall extension walls Form and pour the bridge parapet and safety…