This past week of August 1, 2022, we accomplished the following work: Continued to process steel and concrete removed from the old Eastbound bridge and trucking it off site Completed…
Saturday 7/30/22 The Navigation Channel will be open. Contractor will be onsite continuing steel processing for load out. Contractor will be continuing Pier 2 concrete demolition. Contractor will prepare for…
Saturday 7/23/22 anticipated work is as follows: The Navigation Channel will be open. Contractor will be onsite continuing bridge demolition operations. Contractor will be continuing Pier 2 concrete demolition. Contractor…
On Saturday, 7/16, there will be ongoing concrete removal at Pier 1. Week of 7/11: Completed work this past week included Abutment 1 footing concrete pours and ongoing steel removal…
Saturday, 7/9/2022 The Navigation Channel will be open. The Contractor will be onsite: Relocating and unloading demolition barges Breaking down Abutment 1 temporary steel support to relocate to Abutment 2…
No work is scheduled over the July 4 Holiday weekend. This past week of June 27, the following work was performed: Removal of the deck on the Eastbound Bridge Removal…
This past week of June 20, the following work was accomplished: Continued the demolition of the Eastbound Bridge; removing deck and parapet between Piers 3 and 4 Formed and placed…
This past week of June 13 work performed was as follows: Continued the demolition of the Eastbound Bridge; currently working removing deck and parapet between Piers 2 and 3. Formed…
Completed Work this past Week of 6/06/2022: Continued concrete bridge deck demolition of the Eastbound bridge Continued drainage installation for the Newtown approach to the bridge Continued reinforcing installation for…