We kicked off 2022 by implementing the Westbound Crossover alignment on Jan 4, 2022. The Contractor then performed some further clearing and grubbing which allowed them to construct two temporary access roads to the westbound bridge. TMC and their subcontractors then demolished the Bridge 01218 superstructure and completed concrete pier removal; then they reconstructed the three bridge piers per the contract modification plans.
In August and September they completed steel girder erection. In October they installed the stay-in-place formwork and began deck reinforcing steel installation. Throughout the months of November and December the Contractor completed deck rebar installation and pouring of the concrete deck sections. And finally, over the last two weeks they have been working of forming and pouring the concrete bridge parapets and safety curb.
January 2022:
May 2022:
July 2022:
September 2022:
December 2022: