No work is anticipated on Saturday, June 5.
Next week, from Monday, June 7, work on the project will be as follows:
- Continue placing rebar and pouring concrete for modifications of abutment footings
- Place formwork for the cap at Pier 2
- Continue footing modifications at Pier 3. (The cofferdam has been completed using large sandbags to keep water out of the footing site.)
- Driving pile for temporary supports for future steel erection.
Boaters, please be cautioned that the Project currently maintains a ‘Slow – No Wake’ speed restriction through the channel at all times, even on weekends when there is no work. Read more.