This past week of October 9, we accomplished the following work:
- Continued to grade the temporary re-use stockpile area (TRSA)
- Continued to restore the laydown yard
- Completed final sign installation
- Continued to monitor and control environmental Best Management Practices (BMPs)
Next week of October 16, we plan to accomplished the following work:
- Continue final grading at the TRSA
- Continue final grading at the Fish Rock Road access road
- Begin to remove barrier offsite
- Continue to monitor and control environmental BMPs
Possible night work next week but which nights is not yet confirmed.