This past week of July 16, we accomplished the following work:

  • Continued to restore access roads using material from the temporary re-use stockpile area (TRSA)
  • Continued to install the water quality swale in Southbury & Newtown
  • Completed final paving westbound
  • Continued to restore the medians on the Newtown & Southbury sides
  • Continued to screen topsoil for use on site
  • Continued to monitor and control environmental Best Management Practices (BMPs)

Night work continuing from Sunday, July 23 to Friday, July 28, 6 PM to 6 AM
Working days from Monday, July 24 to Friday, July 28

Next week of July 23, we plan to accomplished the following work:

  • Continue to restore access roads using material from the TRSA
  • Continue to install the water quality swale in Southbury & Newtown
  • Install asphaltic plug joints on westbound Center Street Bridge
  • Install final line striping eastbound & westbound
  • Continued to restore the medians on the Newtown & Southbury sides
  • Continue to monitor and control environmental BMPs