This past week of July 10, we accomplished the following work:

  • Continued to restore access roads using material from the temporary re-use stockpile area (TRSA)
  • Continued to install the water quality swale Southbury & Newtown
  • Completed milling of the westbound roadway
  • Continued to restore the medians on the Newtown & Southbury sides
  • Continued to screen topsoil for use on site
  • Continued to monitor and control environmental Best Management Practices (BMPs)

Night work continuing Sunday, 7-16-23, to Friday 7-21-23 6:00 PM to 6:00 AM
Working days from Monday, 7-17-23, to Friday, 7-21-23

Next week of July 16, we plan to accomplished the following work:

  • Start & complete final paving I-84 WB
  • Continue to restore access roads using material from the TRSA
  • Continue to install the water quality swale Southbury & Newtown
  • Install asphaultic plug joints on westbound Center St. Bridge
  • Continue to restore the medians on the Newtown & Southbury sides
  • Continue to monitor and control environmental BMPs