This past week of December 5, we accomplished the following work:

  • Completed installation of galvanized deck reinforcing steel
  • Completed installation of bridge scuppers
  • Completed and began curing of final deck pours #6 and #7
  • Completed concrete pour for wingwall extension at Abutments 1 & 2
  • Began installation of parapet and safety curb reinforcing steel
  • Continued to form the abutment wingwall extension walls
  • Continued to monitor and control dust, and other environmental BMPs post-rain storms

The Contractor will be working Saturday December 10.

During the week of December 12, we will continue to:

  • Cure final concrete deck sections – Deck Pours 6 & 7
  • Form abutment wingwall extensions walls
  • Form and pour the bridge parapet and safety curb