This past week of December 5, we accomplished the following work:
- Completed installation of galvanized deck reinforcing steel
- Completed installation of bridge scuppers
- Completed and began curing of final deck pours #6 and #7
- Completed concrete pour for wingwall extension at Abutments 1 & 2
- Began installation of parapet and safety curb reinforcing steel
- Continued to form the abutment wingwall extension walls
- Continued to monitor and control dust, and other environmental BMPs post-rain storms
The Contractor will be working Saturday December 10.
During the week of December 12, we will continue to:
- Cure final concrete deck sections – Deck Pours 6 & 7
- Form abutment wingwall extensions walls
- Form and pour the bridge parapet and safety curb